| SERVICE |
FEE |
| g) Sign Code |
A fee for each permit, including related plan checking fees, shall be paid as provided in Table 3-A of the 1988 Edition of the Uniform Building Code. |
| Zone Change and Prezone Fee |
$600.00 |
| Zoning Variance Fees |
$500.00 |
| Annexation Fees |
Actual cost plus 20%, with $1,500.00 minimum |
| Conditional / Temporary Use Permit Fee |
$500.00 |
| General Plan Amendment Fee |
Actual cost plus 20%, with $1,000.00 minimum |
| Tentative and Revised Tentative Map Fee |
$750.00 plus $10.00/lot. Modifications and subdivision requirement shall be $100.00 each. Optional design and improvement standards and Vesting Tentative Map shall be $1,00.00 plus $10.00/lot |
| Appeal Fee |
$10.00 for an appeal relative to an owner occupied single-family dwelling; $175.00 for all others. |
| CEQA - Asessment and Initial Study Fee |
$100.00 |
| CEQA - Negative Declaration Fee |
$140.00 |
| CEQA - EIR Fee |
Actual cost plus 20%, with a $5550.00 minimum. |
| Time Extension Fee |
$80.00 |
| Lot line Adjustment and Parcel Map Waiver Fee |
$230.00 |
| Certificate of Compliance Fee |
$60.00 |
| Final Subdivision and Parcel Map Fee |
$250.00 plus $10.00 per lot. |
| Improvement Plan Engineering Check Fee |
$125.00 plus $40.00/lot for subdivisions;
$125.00 plus $100.00/acre, or portion thereof, for other developments. |
| Subdevision Improvement Inspection Fee |
5% of the first $100,000.00 of estimated value of public improvements; plus 3 1/2% of the improvements over $100,000.00.
Inspection desired outside of normal City Working hours shall be charged at a rate of $30.00 per hour with atwo hour minimum. |
| Development Agreement Charge |
Cost plus 20%, with a $550.00 minimum. |